Ashes Recycling System Realization
Mechanical Realization:
For more details check the mechanical realization page
Mechanical Realization (aecenar.com)
PCS Implementation:
parts needed :
-4 valve
- 4 pipes (4m each)
- 3 medium-sized tanks
- 2 electrical pumps (>1hp)
- 4 moukhalef + wasel zira3e
- 9 turns 90 ppr
- 2 tees ppr
initial cost : ~ 200 $
For more details check the PCS implementation page
PCS Implementation (aecenar.com)