NLAP-Biogas test 5_18012024:Enhancing Methane storage through Gas Compression with filtration systempart 2

 

 

Step Step description    Expected Result  Result    Result Description
Precondition  ❌ ✔  
System is off all Valves are closed System is off   ✔  
Connection  
Connecting gas entrance Connect the PEX tube to the compression machine inlet (manually) Connected   ✔  
connecting check valve Connect the check valve to the machine outlet (manually) connected   ✔  
Connecting the system to the gas storage tank Connect the pipe in the machine outlet to the methane gas storage (manually) connected   ✔  
Leakage check start the compressor and open Valves V1 and V2 and Gas Tank main Valve to check the leakage in the system (with Soap) no leak   ✔  
close the compressor and close the Valves V1 and V2 and Gas Tank main Valve no obstacles   ✔  
Test Starts
0pen gas tank open the gas tank main valve (manually) opened   ✔  
open V1 open the Valve (V1) (manually) no obstacles   ✔  
open  V2 , V3, V4, V5 Open Valve V2 , V3, V4, V5 of the Biogas (manually) gas inlet should be equal gas outlet    ✔  
 start the Switch of the compressor  start the switch of the compressor (by GUI) compression started (and compression ended by the Compressor switch when it reaches 8 bar (on PG2) or when the pressure at the biogas reaches atmospheric pressure (by PS) )   ✔ switch reached 8 bar pressure and system turned off
Close the red emergency switch of the compressor Close the red switch of the compressor (manually) in case of emergency when neither the switch turned off automatically nor the GUI gives the order to close the system cycle Compressor turned off ❌   we didn’t use it
close  V2 , V3, V4, V5 close the Valve V2 , V3, V4, V5 of the Biogas (manually) no obstacles   ✔  
close V1 close the Valve (V1) (manually) no obstacles   ✔  
Post condition 
System is off all Valves are closed System is off   ✔  

 

0

 

 

Full video of the biogas Process: Video18012024