Batroun Waste Management 2024
1. NLAP-WEDC Part I (March - June 2024)
Moving from Ras Maska to Batroun and Commisioning of:
- Mobile Waste Separation Module (max. 3 tons municipal / day)
- Mobile Biogas Generation Module (14,000 Liter) (max. 10 tons organic waste)
About 90% water
1 ton biowaste, which produces about 2000 m^3 methan gas in 1 month.
Needed Place: 500 qm
Costs: 10,000 $ / month
2. NLAP-WEDC Part II (April - June 2024)
- Mobile Waste Incineration Power Plant Module (max. 2 tons refused waste per day / 25 kW)
Needed Infrastructure: Cooling water (pipes to sea)
Needed place: 1000 qm
Costs: 8,000 $ / month
3. Installing of 50 tons / day waste management system, Generation of 2 MW Electricity and of 2 Megaliter Biogas per day (July 2024 - April 2025)
- Waste Separation Unit 50 tons/day capacity (0,3 Mio $)
similar to:
Dialas_waste_sorting_plant_02082023_Poster.jpg (2246×3178) (aecenar.com)
- Biogas tank field (30 x 300,000 Liter tanks) (30 x 0,03 Mio $ = 0,9 Mio$), similar to:
Biogas & fertilizer productions at Aassoun POSTER (pptx)
Biogas & fertilizer productions at Aassoun POSTER (pdf)
- Waste Incineration Power Plant (Costs: 4,5 Mio $)
Costs: About 5,7 Mio$
Needed Infrastructure: Cooling water (pipes to sea)
Needed place: 5000 qm